Pembebasan Lahan MRT Ditargetkan Rampung Desember
.
photo Reza Hapiz - Beritajakarta.id

MRT Land Buying Process Targeted to Complete December

The construction of MRT Lebak Bulus-Bundaran Hotel Indonesia route phase 1 is still disturbed by land buying process. Now, several land owners have agreed with the loan-use agreement. It is targeted to complete the land buying in December.

Our problem is for 127 land lots. I think it can be solved in mid December

Acting Jakarta Governor, Sumarsono, said 281 land lots need to be bought, but only 127 are priorities. The budget has been prepared in 2016 city budget.

“Our problem is for 127 land lots. I think it can be solved in mid December,” he said, Tuesday (11/15).

Acting Governor Satisfied with Progress of MRT Project

The budget has been prepared in Dept. of Bina Marga and Dept. of Transportation. He hoped the project will finish on time since it is a national project. If this project is complete, second phase Bundaran HI-Kampung Bandan (Ancol TImur) construction can be run.

“So let’s support the program for our pride too,” he closed.

Linked News
Popular News indeks
  1. Pramono Prioritizes Construction of Cakung Regional Hospital

    access_time18-04-2025 remove_red_eye468 personFakhrizal Fakhri
  2. Governor Pramono Joins Cycling in Jakarta Silaturahride 2025

    access_time19-04-2025 remove_red_eye408 personBudhi Firmansyah Surapati
  3. Jakarta to Make Public Transportation Free on April 24, 2025

    access_time18-04-2025 remove_red_eye320 personAldi Geri Lumban Tobing
  4. City Goverment Encourages Residents to Use Public Transportation

    access_time21-04-2025 remove_red_eye284 personFakhrizal Fakhri
  5. Transjakarta Applies Special Fares for Female Customers

    access_time20-04-2025 remove_red_eye266 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik